Statuscompleted
Stagecomplete
StartJun 2022
CompletionJun 2023
Budget$877,000
CityNew York
AddressMid block on West 28th Street between 9th Avenue and 10th Avenue
SourceNYC Parks CIP
Source IDnyc_parks_cip:9348
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2023-06-01
Construction completion (projected)2023-06-01
Design % complete100.0
Design complete (actual)2020-04-01
Design start2019-04-01
FMS ID846 P-304CBBC
Funding sourceCity Council
Park IDM011
Procurement % complete100.0
Procurement complete (actual)2022-06-01
Procurement start2020-04-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the basketball court and adjacent paths and landscape at Chelsea Park.
Total funding (as published)$877,000