| Status | completed |
|---|---|
| Stage | complete |
| Start | Apr 2021 |
| Completion | Dec 2022 |
| Budget | $6,391,000 |
| City | New York |
| Address | Kent Avenue between North 11th Street and North 12th Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:8955 |
| Borough | Brooklyn |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2022-12-01 |
| Construction completion (adjusted) | 2022-12-01 |
| Construction completion (projected) | 2022-04-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2019-08-01 |
| Design start | 2018-06-01 |
| FMS ID | 846 P-2GPWBKT |
| Funding source | Mayoral |
| Park ID | B529 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2021-03-01 |
| Procurement start | 2019-08-01 |
| Project liaison | James Morris |
| Summary | This project will construct a portion of Bushwick Inlet Park at 50 Kent Avenue. |
| Total funding (as published) | $6,391,000 |