Bleecker Playground and Public Restroom Building Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartSep 2012
CompletionAug 2013
Budget$473,000
CityNew York
AddressBleecker Street, Hudson Street, West 11th Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:2177
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2013-08-01
Construction completion (adjusted)2013-09-01
Construction completion (projected)2013-09-01
Design % complete100.0
Design complete (actual)2011-01-01
Design start2009-02-01
FMS ID846 P-302BLEK
Funding sourceCity Council
Park IDM251
Procurement % complete100.0
Procurement complete (actual)2012-07-01
Procurement start2011-01-01
Project liaisonSteve Simon
SummaryThis project will reconstruct Bleecker Playground, including the Public Restroom Building.
Total funding (as published)$473,000