| Status | completed |
|---|---|
| Stage | complete |
| Start | Sep 2012 |
| Completion | Aug 2013 |
| Budget | $473,000 |
| City | New York |
| Address | Bleecker Street, Hudson Street, West 11th Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:2177 |
| Borough | Manhattan |
| Construction % complete | 100.0 |
| Construction completion (actual) | 2013-08-01 |
| Construction completion (adjusted) | 2013-09-01 |
| Construction completion (projected) | 2013-09-01 |
| Design % complete | 100.0 |
| Design complete (actual) | 2011-01-01 |
| Design start | 2009-02-01 |
| FMS ID | 846 P-302BLEK |
| Funding source | City Council |
| Park ID | M251 |
| Procurement % complete | 100.0 |
| Procurement complete (actual) | 2012-07-01 |
| Procurement start | 2011-01-01 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct Bleecker Playground, including the Public Restroom Building. |
| Total funding (as published) | $473,000 |