Bellevue South Park Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartMay 2022
CompletionJun 2023
Budget$3,945,000
CityNew York
Address1st Avenue, Mount Carmel Place, East 26th Street, East 28th Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:8826
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2023-06-01
Construction completion (projected)2023-05-01
Design % complete100.0
Design complete (actual)2019-12-01
Design start2018-07-01
FMS ID846 P-3BELLVU
Funding sourceBorough PresidentCity CouncilMayoral
Park IDM263
Procurement % complete100.0
Procurement complete (actual)2022-03-01
Procurement start2019-12-01
Project liaisonSteve Simon
SummaryThis project will construct an ADA-accessible dog run and reconstruct the basketball court, playground, and sitting areas at Bellevue South Park.
Total funding (as published)$3,945,000