Construction Project Update

Baruch Playground Public Restroom Building Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartAug 2018
CompletionDec 2021
Budget$1,909,000
CityNew York
AddressBaruch Place and Rivington Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:6389
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2021-12-01
Construction completion (adjusted)2021-10-01
Construction completion (projected)2020-01-01
Design % complete100.0
Design complete (actual)2017-01-01
Design start2015-12-01
FMS ID846 P-303BPCS
Funding sourceCity CouncilMayoral
Park IDM165
Procurement % complete100.0
Procurement complete (actual)2018-05-01
Procurement start2017-01-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the public restroom building at Baruch Playground.
Total funding (as published)$1,909,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.