Asser Levy Playground Expansion

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartOct 2013
CompletionOct 2014
Budget$1,293,000
CityNew York
AddressAsser Levy Place between East 23rd Street and East 25th Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:5961
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2014-10-01
Construction completion (adjusted)2014-10-01
Construction completion (projected)2014-10-01
Design % complete100.0
Design complete (actual)2013-05-01
Design start2012-04-01
FMS ID846 P-306ALNP
Funding sourceCity Council, Private
Park IDM164
Procurement % complete100.0
Procurement complete (actual)2013-09-01
Procurement start2013-05-01
Project liaisonSteve Simon
SummaryThis project will expand Asser Levy Playground into the roadbed of Asser Levy Place and construct a new artificial turf field and exercise track, new adult fitness equipment, benches, tables, drinking
Total funding (as published)$1,293,000

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

Nothing since we started tracking this project. We check every morning.