Statuscompleted
Stagecomplete
StartMar 2018
CompletionSep 2019
Budget$2,369,000
CityNew York
AddressFifth Avenue and East 64th Street
SourceNYC Parks CIP
Source IDnyc_parks_cip:6297
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2019-09-01
Construction completion (projected)2019-09-01
Design % complete100.0
Design complete (actual)2017-03-01
Design start2015-05-01
FMS ID846 P-313CPAB
Funding sourceMayoral
Park IDM010
Procurement % complete100.0
Procurement complete (actual)2018-01-01
Procurement start2017-03-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the facade and roof at the Arsenal building in Central Park.
Total funding (as published)$2,369,000