Albano Playground Reconstruction

New York · NYC Parks CIP

This city’s feed has changed within the last week. We check every morning.

Statuscompleted
Stagecomplete
StartNov 2023
CompletionOct 2024
Budget$1,550,000
CityNew York
AddressEast 29th Street and 2nd Avenue
SourceNYC Parks CIP
Source IDnyc_parks_cip:6365
BoroughManhattan
Construction % complete100.0
Construction completion (actual)2024-10-01
Construction completion (projected)2024-11-01
Design % complete100.0
Design complete (actual)2022-04-01
Design start2015-09-01
FMS ID846 P-306APMU
Funding sourceBorough President, City Council
Park IDM265
Procurement % complete100.0
Procurement complete (actual)2023-09-01
Procurement start2022-04-01
Project liaisonSteve Simon
SummaryThis project will reconstruct the play equipment, safety surfacing, handball courts, and asphalt multi-purpose play area and construct a new spray shower at Albano Playground.
Total funding (as published)$1,550,000