24 Sycamores Playground Handball, Basketball and Play Equipment Reconstruction
New York · NYC Parks CIP
This city’s feed has changed within the last week. We check every morning.
| Status | design |
|---|---|
| Stage | design |
| City | New York |
| Address | York Avenue between East 60th Street and East 61st Street |
| Source | NYC Parks CIP |
| Source ID | nyc_parks_cip:10602 |
| Borough | Manhattan |
| Construction % complete | 0.0 |
| Design % complete | 100.0 |
| Design complete (actual) | 2026-10-01 |
| Design start | 2025-03-01 |
| FMS ID | 846 P-3SYCAMO |
| Funding source | Borough President, City Council, Private |
| Park ID | M108Q |
| Procurement % complete | 0.0 |
| Project liaison | Steve Simon |
| Summary | This project will reconstruct the Handball, Basketball and Play Equipment at 24 Sycamores Playground. |
| Total funding (as published) | Between $3 million and $5 million |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
Nothing since we started tracking this project. We check every morning.