StatusDesign
Stagedesign
StartSep 2027
CompletionAug 2028
Budget$1,482,007
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:7297
Active phaseDesign
Construction % complete0
Contact[email protected]
Council district(s)1 - Eunisses Hernandez
Design start (scheduled)2021-05-27
Map pieces1
Phase % complete91
ProgramStreet Improvement
Project managerMina Grais
Project numberM1099
ScopeThe Valencia Triangle Streetscape Improvement Project a is a Federal Grant Project located on 8th Street between Valencia Street and Green Street. The improvements consist of replacing 6,000 SFT of fr
Work orderE1908825

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-08-17Majorstart date slipped ~5 months
2026-08-07Majorbudget raised 45% ($1,019,947 -> $1,482,007)