Construction Project Update

Taylor Yard Paseo del Rio & Proposition O Water Quality Improvements

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusDesign
Stagedesign
StartNov 2028
CompletionMay 2031
Budget$65,678,989
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:7478
Active phaseDesign
Construction % complete0
Contact[email protected]
Council district(s)1 - Eunisses Hernandez
Design start (scheduled)2024-04-23
Map pieces1
Phase % complete62
ProgramProp O
Project managerElena Lopez
Project number0/01-87
ScopeThe Paseo del Rio & Taylor Yard G2 Water Quality Improvements Project remediates and develops a part of the G2 parcel of the former Union Pacific Railroad Company (UP) rail yard into habitat-focused o
Work orderEW40087A

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-07-29Majorcompletion date slipped ~1.5 years