SR 710 Valley Bl Multi Modal Transportation Improvements

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusDesign
Stagedesign
StartMar 2028
CompletionSep 2030
Budget$121,800,000
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:7438
Active phaseDesign
Construction % complete0
Contact[email protected]
Council district(s)14 - Ysabel J. Jurado
Design start (scheduled)2024-11-14
Map pieces2
Phase % complete70
ProgramBridge Improvement Program
Project managerErik Munoz
Project numberXX11
ScopeThe SR 710 Valley Bl Multi-Modal Transportation Improvements (Project) lies along a 4.5-mile section of Valley Boulevard and Mission Road between the SR 710 terminus and Union Station. The Project wil
Work orderE700417A

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-08-12Routinestart date nudged 1 day(s)
2026-08-04Majorstart date slipped ~5 months
2026-07-29Routinestart date nudged 1 day(s)