Sidewalk Repair Program - Package No. 70: Access Request Sites
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Construction |
|---|---|
| Stage | active |
| Start | Dec 2024 |
| Completion | Oct 2026 |
| Budget | $2,092,601 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:7994 |
| Active phase | Construction |
| Construction % complete | 99 |
| Contact | [email protected] |
| Council district(s) | VR - |
| Design start (scheduled) | 2024-01-02 |
| Map pieces | 57 |
| Phase % complete | 99 |
| Program | Sidewalk Repair |
| Project manager | Kevin Gibson |
| Project number | SP109 |
| Scope | Sidewalk repairs and accessibility upgrades of pedestrian facilities at 34 sites. |
| Work order | E1909083 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-08-10 | Major | completion date slipped ~3 months |