Safety Railing near 1780 Rotary Drive
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Pre-Design |
|---|---|
| Stage | planned |
| Start | Aug 2028 |
| Completion | Jul 2029 |
| Budget | $75,000 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:7782 |
| Active phase | Pre-Design |
| Construction % complete | 0 |
| Contact | [email protected] |
| Council district(s) | 13 - Hugo Soto-Martinez |
| Design start (scheduled) | 2027-01-01 |
| Map pieces | 1 |
| Phase % complete | 93 |
| Program | Street Improvement |
| Project manager | Kayla Peji |
| Project number | M1162 |
| Scope | This project will install a handrail onto the curbing wall along the stairway currently connecting Rotary Drive to Redesdale Ave in a hillside area. The public stairway is built on top of an existing |
| Work order | E1909018 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-08-17 | Major | start date slipped ~6 months |