NOS Rehab Unit 11 - Humboldt St to Cardinal St

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusConstruction
Stageactive
StartJun 2025
CompletionSep 2027
Budget$22,880,772
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:4709
Active phaseConstruction
Construction % complete55
Contact[email protected]
Council district(s)1 - Eunisses Hernandez, 14 - Ysabel J. Jurado
Design start (scheduled)2020-05-01
Map pieces14
Phase % complete55
ProgramWastewater - CSP
Project managerNathan Ho
Project numberC820
ScopeThis project will rehabilitate a total of 3,860 linear feet of the 54-inch Burns McDonnell semi-elliptical (BMSE) shaped North Outfall Sewer (NOS) from Diversion Structure 495-09-121 on Humboldt Stree
Work orderSZC13729

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-08-25Majorcompletion date slipped ~3 months