MacArthur Lake Stormwater Capture Project
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Bid & Award |
|---|---|
| Stage | design |
| Start | Jan 2027 |
| Completion | Dec 2029 |
| Budget | $26,691,000 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:7043 |
| Active phase | Bid & Award |
| Construction % complete | 0 |
| Contact | [email protected] |
| Council district(s) | 1 - Eunisses Hernandez |
| Design start (scheduled) | 2023-09-01 |
| Map pieces | 6 |
| Phase % complete | 65 |
| Program | Safe Clean Water |
| Project manager | Brandon Kawaguchi |
| Project number | 1920R004 |
| Scope | The MacArthur Lake Stormwater Capture Project is designed to capture, store, and treat stormwater to sustainably replenish the lake, directly offsetting current potable water use. Beyond local park be |
| Work order | S343MSWC |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-07-30 | Major | completion date slipped ~7 months |