Construction Project Update

Lincoln Park Neighborhood Green Street Network

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusDesign
Stagedesign
StartJun 2029
CompletionSep 2031
Budget$24,124,846
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:7653
Active phaseDesign
Construction % complete0
Contact[email protected]
Council district(s)1 - Eunisses Hernandez, 14 - Ysabel J. Jurado
Design start (scheduled)2025-11-01
Map pieces8
Phase % complete32
ProgramSafe Clean Water
Project managerAmir Kashfi
Project numberSCWLPNP
ScopeThe scope of work includes: implement 46 drywells to capture stormwater flow, plant 500 trees, install 16vegetated medians and 1,100 parkway planters. The parkway planters, vegetated medians, and stre
Work orderS33WLPNP

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-08-21Criticalbudget raised 72% ($14,000,000 -> $24,124,846)
2026-07-29Routinestart date nudged 1 day(s)
2026-07-27Majorcompletion date slipped ~1.6 years