HSIP-Cycle 7: 23 RRFB and 1 HAWK Citywide Formerly (28 RRFB Citywide)

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusConstruction
Stageactive
StartApr 2022
CompletionMar 2027
Budget$6,500,385
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:6147
Active phaseConstruction
Construction % complete87
Contact[email protected]
Council district(s)1 - Eunisses Hernandez, 2 - Adrin Nazarian, 4 - Nithya Raman, 6 - Imelda Padilla, 8 - Marqueece Harris-Dawson, 9 - Curren D. Price, Jr. , 11 - Traci Park, 13 - Hugo Soto-Martinez, 14 - Ysabel J. Jurad
Design start (scheduled)2018-01-25
Map pieces47
Phase % complete87
ProgramStreet Improvement
Project managerFadi Abboud
Project numberM891
ScopeConstruction at multiple locations with RRFB's, access ramp upgrades, median island improvements, and sign & striping modifications at 24 locations. CD 1: (Bonnie Brae St. and James M. Wood Blvd.), (K
Work orderE1908266

Open this project on the city’s own site →

What has changed

Nothing since we started tracking this project. We check every morning.