Hollenbeck Sewer Rehab
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Design |
|---|---|
| Stage | design |
| Start | Jan 2029 |
| Completion | Jun 2031 |
| Budget | $13,691,000 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:7671 |
| Active phase | Design |
| Construction % complete | 0 |
| Contact | [email protected] |
| Council district(s) | 14 - Ysabel J. Jurado |
| Design start (scheduled) | 2026-03-03 |
| Map pieces | 3 |
| Phase % complete | 27 |
| Program | Wastewater - CSP |
| Project manager | Matias Farfan |
| Project number | C1063 |
| Scope | This project will remove and replace approximately 1,747 LF of existing 18-in diameter and rehab 291 LF of an 8-in diameter vitrified clay pipe (VCP) in the Lincoln Heights Primary Sewer Basin (PSB). |
| Work order | SZC14544 |
Open this project on the city’s own site →
What has changed
Nothing since we started tracking this project. We check every morning.