ESDR - 608 S SPRING ST
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Bid & Award |
|---|---|
| Stage | design |
| Start | Mar 2027 |
| Completion | Mar 2028 |
| Budget | $25,000 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:8933 |
| Active phase | Bid & Award |
| Construction % complete | 0 |
| Contact | [email protected] |
| Council district(s) | 14 - Ysabel J. Jurado |
| Map pieces | 1 |
| Phase % complete | 63 |
| Program | Stormwater Conveyance |
| Project manager | Matthew Quintanilla |
| Project number | J1167 |
| Scope | Secure site, and perform repairs as necessary. |
| Work order | SZS12135 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-23 | added |