ESDR - 308 North Avenue 21-CB
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Bid & Award |
|---|---|
| Stage | design |
| Start | Feb 2027 |
| Completion | Feb 2028 |
| Budget | $25,000 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:8903 |
| Active phase | Bid & Award |
| Construction % complete | 0 |
| Contact | [email protected] |
| Council district(s) | 1 - Eunisses Hernandez |
| Map pieces | 1 |
| Phase % complete | 66 |
| Program | Stormwater Conveyance |
| Project manager | Matthew Quintanilla |
| Project number | J1143 |
| Scope | This Emergency Storm Drain Repair (ESDR) project will perform an initial investigation to assess the existing catch basin and make repairs or replacement as necessary. |
| Work order | SZS12111 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-23 | added | |
| 2026-10-23 | Routine | 44 projects added — catalog expansion (9% of 510 rows) |