Elysian Valley Shared Path Improvement
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Design |
|---|---|
| Stage | design |
| Start | Jan 2028 |
| Completion | Mar 2029 |
| Budget | $1,965,701 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:6738 |
| Active phase | Design |
| Construction % complete | 0 |
| Contact | [email protected] |
| Council district(s) | 13 - Hugo Soto-Martinez |
| Design start (scheduled) | 2020-10-01 |
| Map pieces | 1 |
| Phase % complete | 90 |
| Program | LA River Projects |
| Project manager | Kayla Gailing |
| Project number | LAR03 |
| Scope | The Project will provide pedestrian safety measures to a portion of the existing Los Angeles River shared path that is used by cyclists and pedestrians in the Elysian Valley neighborhood from Dallas S |
| Work order | E1908510 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-06 | Notable | budget raised 12% ($1,750,000 -> $1,965,701) |
| 2026-09-03 | Notable | budget cut 9% ($1,916,688 -> $1,750,000) |
| 2026-07-31 | Major | completion date slipped ~1.0 years |
| 2026-07-30 | Notable | completion date moved earlier (2028-12-31 -> 2028-03-31) |