City Hall Chamber Council Restroom Addition

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusConstruction
Stageactive
StartJan 2026
CompletionNov 2026
Budget$267,794
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:8213
Active phaseConstruction
Construction % complete72
Contact[email protected]
Council district(s)14 - Ysabel J. Jurado
Design start (scheduled)2024-11-02
Map pieces1
Phase % complete72
ProgramMunicipal Facilities Architect
Project managerJenny Lim
Project numberG1243
ScopeRenovate existing Chamber Council Media / Breakroom to include an additional women's accessible single occupancy restroom.
Work orderE1909651

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-08-19Notablebudget raised 34% ($200,000 -> $267,794)