| Status | Bid & Award |
|---|---|
| Stage | design |
| Start | May 2027 |
| Completion | Apr 2029 |
| Budget | $14,890,154 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:6715 |
| Active phase | Bid & Award |
| Construction % complete | 0 |
| Contact | [email protected] |
| Council district(s) | 14 - Ysabel J. Jurado |
| Design start (scheduled) | 2020-12-01 |
| Map pieces | 1 |
| Phase % complete | 61 |
| Program | Wastewater - CSP |
| Project manager | Alyssa Reyes |
| Project number | C1012 |
| Scope | This project will rehabilitate approximately 5,035 linear feet of 36-inch and 38-inch existing circular sewers in the Central Business District with CIPP or UV-CIPP lining. The alignment of this reach |
| Work order | SZC13941 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-07-31 | Major | start date slipped ~6 months |