StatusBid & Award
Stagedesign
StartMay 2027
CompletionApr 2029
Budget$14,890,154
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:6715
Active phaseBid & Award
Construction % complete0
Contact[email protected]
Council district(s)14 - Ysabel J. Jurado
Design start (scheduled)2020-12-01
Map pieces1
Phase % complete61
ProgramWastewater - CSP
Project managerAlyssa Reyes
Project numberC1012
ScopeThis project will rehabilitate approximately 5,035 linear feet of 36-inch and 38-inch existing circular sewers in the Central Business District with CIPP or UV-CIPP lining. The alignment of this reach
Work orderSZC13941

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-07-31Majorstart date slipped ~6 months