CBD Sewer Rehab Unit 11A - 6th St Siphon to Santa Fe Ave
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Construction |
|---|---|
| Stage | active |
| Start | Jun 2023 |
| Completion | Oct 2026 |
| Budget | $1,206,997 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:7463 |
| Active phase | Construction |
| Construction % complete | 99 |
| Contact | [email protected] |
| Council district(s) | 14 - Ysabel J. Jurado |
| Design start (scheduled) | 2021-12-01 |
| Map pieces | 4 |
| Phase % complete | 99 |
| Program | Wastewater - CSP |
| Project manager | Jin Wen |
| Project number | C1042 |
| Scope | Rehabilitate approximately 477 linear feet of existing 36-inch circular sewers in the Central Business District by ultra violet cured-in-place pipe(UV CIPP). The alignment of the reach begins at the 6 |
| Work order | SZC14224 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-13 | Notable | completion date slipped ~3 weeks |