BSS - Package 65
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Construction |
|---|---|
| Stage | active |
| Start | Jun 2026 |
| Completion | Jun 2027 |
| Budget | $373,463 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:8449 |
| Active phase | Construction |
| Construction % complete | 35 |
| Contact | [email protected] |
| Council district(s) | AL - |
| Design start (scheduled) | 2025-09-24 |
| Map pieces | 158 |
| Phase % complete | 35 |
| Program | Sidewalk Repair |
| Project manager | David Ventura |
| Project number | SP162 |
| Scope | This project includes Access Request sites located near LA28 venues and focuses on removing sidewalk and curb ramp barriers identified by individuals with mobility disabilities. All construction work |
Open this project on the city’s own site →
What has changed
Nothing since we started tracking this project. We check every morning.