StatusConstruction
Stageactive
StartJun 2026
CompletionJun 2027
Budget$373,463
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:8449
Active phaseConstruction
Construction % complete35
Contact[email protected]
Council district(s)AL -
Design start (scheduled)2025-09-24
Map pieces158
Phase % complete35
ProgramSidewalk Repair
Project managerDavid Ventura
Project numberSP162
ScopeThis project includes Access Request sites located near LA28 venues and focuses on removing sidewalk and curb ramp barriers identified by individuals with mobility disabilities. All construction work

Open this project on the city’s own site →