Benjamin Franklin Library Renovations

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusConstruction
Stageactive
StartNov 2025
CompletionMay 2027
Budget$5,500,000
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:7660
Active phaseConstruction
Construction % complete65
Contact[email protected]
Council district(s)14 - Ysabel J. Jurado
Design start (scheduled)2023-10-04
Map pieces2
Phase % complete65
ProgramMunicipal Facilities Architect
Project managerSeda Yeghiyan
Project numberG1194
ScopeDesign and construction of new tenant improvements, new programs such as Adult Literacy & New Americans Centers, structural upgrades for known structural deficiencies, adjustments to the building egre
Work orderE1908948

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-09-23Majorcompletion date slipped ~4 months