Avon Street (1923) Bulkhead

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusConstruction
Stageactive
StartMar 2026
CompletionDec 2026
Budget$646,000
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:8182
Active phaseConstruction
Construction % complete86
Contact[email protected]
Council district(s)13 - Hugo Soto-Martinez
Design start (scheduled)2025-02-01
Map pieces1
Phase % complete86
ProgramHillside Slope Stability
Project managerDaniel Orris
Project numberM1225
ScopeThis project will install a new steel beam and pre-cast lagging bulkhead (H=4.5-ft, L=70-ft) and regrade the roadway to drain away from the slope (L=100-ft, W=21-ft)
Work orderE1909302

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-10-16Majorcompletion date slipped ~2 months