ATP 6: SRTS Center City Schools Neighborhood Safety and Climate Resilience Project

Los Angeles · LA BOE CIP

This city’s feed has changed within the last week. We check every morning.

StatusPre-Design
Stageplanned
StartApr 2029
CompletionMar 2031
Budget$29,767,000
CityLos Angeles
SourceLA BOE CIP
Source IDla_boe_cip:8242
Active phasePre-Design
Construction % complete0
Contact[email protected]
Council district(s)1 - Eunisses Hernandez, 10 - Heather Hutt, 13 - Hugo Soto-Martinez
Design start (scheduled)2026-09-01
Map pieces1
Phase % complete97
ProgramStreet Improvement
Project managerJoe Linn
Project numberM1230
ScopeThis project will create 5.9 miles of low-stress streets with pedestrian/bicycle improvements in the City's dense residential and commercial core, connecting DAC students/residents with schools, trans
Work orderE1909293

Open this project on the city’s own site →

What has changed

SeenRankChange
2026-08-17Routinestart date nudged 3 day(s)
2026-08-10Majorstart date slipped ~2 months