ATP 6: SRTS Center City Schools Neighborhood Safety and Climate Resilience Project
Los Angeles · LA BOE CIP
This city’s feed has changed within the last week. We check every morning.
| Status | Pre-Design |
|---|---|
| Stage | planned |
| Start | Apr 2029 |
| Completion | Mar 2031 |
| Budget | $29,767,000 |
| City | Los Angeles |
| Source | LA BOE CIP |
| Source ID | la_boe_cip:8242 |
| Active phase | Pre-Design |
| Construction % complete | 0 |
| Contact | [email protected] |
| Council district(s) | 1 - Eunisses Hernandez, 10 - Heather Hutt, 13 - Hugo Soto-Martinez |
| Design start (scheduled) | 2026-09-01 |
| Map pieces | 1 |
| Phase % complete | 97 |
| Program | Street Improvement |
| Project manager | Joe Linn |
| Project number | M1230 |
| Scope | This project will create 5.9 miles of low-stress streets with pedestrian/bicycle improvements in the City's dense residential and commercial core, connecting DAC students/residents with schools, trans |
| Work order | E1909293 |
Open this project on the city’s own site →
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-08-17 | Routine | start date nudged 3 day(s) |
| 2026-08-10 | Major | start date slipped ~2 months |