Spann St: San Felipe St to Mimosa Dr: Neighborhood Sewer System Improvements
Houston · Houston CIP
This city’s feed has changed within the last week. We check every morning.
| Status | E |
|---|---|
| Stage | design |
| Start | Aug 2027 |
| Completion | Sep 2028 |
| City | Houston |
| Source | Houston CIP |
| Source ID | houston_cip:R-002011-0089|M-410033-0001|Spann St: San Felipe St to Mimosa Dr: Neighborhood Sewer System Improvements |
| Category | Street and Traffic |
| District | G |
| Key map | 492Q |
| Stage | Engineering |
| Type | NLSR |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-09-23 | Major | start date slipped ~2 months |