| Status | C |
|---|---|
| Stage | active |
| Start | Feb 2025 |
| Completion | Apr 2026 |
| City | Houston |
| Source | Houston CIP |
| Source ID | houston_cip:S-000035-0269|S-000035-0269|Midtown Area and Willow, Dearborn, Montlew and Lancaster Place Subdivisions : Watermain Replacement |
| Category | Water |
| District | G |
| Key map | 493W |
| Stage | Construction |
| Type | SWLR |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-07 | Notable | completion date slipped ~6 weeks |