State-Thomas - Flora/Boll to Fairmont

Dallas · Dallas Bonds

This city’s feed has changed within the last week. We check every morning.

StatusAwarded for Construction
Stagedesign
StartAug 2026
CompletionFeb 2027
Budget$1,605,284
CityDallas
SourceDallas Bonds
Source IDdallas_bonds:1013098
Amount paid$77,377
Bond amount$495,000
CategoryStorm Drainage
Construction award2025-09-24
Current commitment$503,850
Design award2019-10-23
Design complete2024-01-24
District(s)14
Original budget$495,000
ProgramFlood Protection and Storm Drainage
Program year2017
Project IDTW17VD45

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-07-31Notablestart date slipped ~2 months