Stafford Park - Playground and park furnishings

Dallas · Dallas Bonds

This city’s feed has changed within the last week. We check every morning.

StatusUnder Design
Stagedesign
StartOct 2026
CompletionApr 2027
Budget$34,618
CityDallas
SourceDallas Bonds
Source IDdallas_bonds:1012770
Amount paid$14,500
Bond amount$220,000
CategoryPlayground Improvement
Construction award2026-09-30
Current commitment$30,349
Design award2021-06-07
Design complete2026-07-31
District(s)06
Original budget$220,000
ProgramPark and Recreation Facilities
Program year2017
Project IDPK17VB79

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-08-14Notablestart date slipped ~2 months
2026-07-31Notablecompletion date slipped ~4 weeks