Construction Project Update

Klyde Warren Park - Site Development (CD14)

Dallas · Dallas Bonds

This city’s feed has changed within the last week. We check every morning.

StatusUnder Design
Stagedesign
Budget$1,000,000
CityDallas
SourceDallas Bonds
Source IDdallas_bonds:1020570
Bond amount$1,000,000
CategoryCDSF
Current commitment$1,003,647
Design award2024-09-01
Design complete2026-09-01
District(s)14
Original budget$1,000,000
ProgramPark and Recreation Facilities
Program year2024
Project IDPK24YB45

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-07-30added
2026-07-30Routinenew design-stage project appeared