Katy Trail - Fairmount/Maple Entr (New); Knox to Harvard Trl
Dallas · Dallas Bonds
This city’s feed has changed within the last week. We check every morning.
| Status | Under Design |
|---|---|
| Stage | design |
| Start | May 2029 |
| Completion | Dec 2029 |
| Budget | $200,000 |
| City | Dallas |
| Source | Dallas Bonds |
| Source ID | dallas_bonds:1020372 |
| Bond amount | $1,000,000 |
| Category | Partnership Matches (Large Matches) |
| Construction award | 2029-02-28 |
| Current commitment | $5,085 |
| Design award | 2027-12-31 |
| Design complete | 2028-10-31 |
| District(s) | 02,14 |
| Original budget | $1,000,000 |
| Program | Park and Recreation Facilities |
| Program year | 2024 |
| Project ID | PK24YB85 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-07-28 | Major | completion date slipped ~2.1 years |