| Status | Awarded for Construction |
|---|---|
| Stage | design |
| Start | Jun 2026 |
| Completion | Oct 2026 |
| Budget | $857,849 |
| City | Dallas |
| Source | Dallas Bonds |
| Source ID | dallas_bonds:1013072 |
| Amount paid | $52,543 |
| Bond amount | $820,000 |
| Category | Storm Drainage |
| Construction award | 2024-05-22 |
| Current commitment | $102,829 |
| Design award | 2019-10-09 |
| Design complete | 2023-08-21 |
| District(s) | 02 |
| Original budget | $820,000 |
| Program | Flood Protection and Storm Drainage |
| Program year | 2017 |
| Project ID | TW17VD39 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-05 | Major | budget raised 53% ($560,589 -> $857,849) |
| 2026-10-02 | Major | budget raised 113% ($263,329 -> $560,589) |