Junius Street @Baylor University Medical Center

Dallas · Dallas Bonds

This city’s feed has changed within the last week. We check every morning.

StatusAwarded for Construction
Stagedesign
StartJun 2026
CompletionOct 2026
Budget$857,849
CityDallas
SourceDallas Bonds
Source IDdallas_bonds:1013072
Amount paid$52,543
Bond amount$820,000
CategoryStorm Drainage
Construction award2024-05-22
Current commitment$102,829
Design award2019-10-09
Design complete2023-08-21
District(s)02
Original budget$820,000
ProgramFlood Protection and Storm Drainage
Program year2017
Project IDTW17VD39

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-05Majorbudget raised 53% ($560,589 -> $857,849)
2026-10-02Majorbudget raised 113% ($263,329 -> $560,589)