StatusUnder Design
Stagedesign
StartSep 2026
CompletionDec 2026
Budget$1,200,000
CityDallas
SourceDallas Bonds
Source IDdallas_bonds:1020562
Bond amount$300,000
CategoryCDSF
Construction award2026-08-01
Current commitment$251,570
Design award2024-10-01
Design complete2026-04-01
District(s)06
Original budget$300,000
ProgramPark and Recreation Facilities
Program year2024
Project IDPK24YB37

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-08Majorbudget raised 100% ($600,000 -> $1,200,000)
2026-08-14Notablebudget set ($600,000)
2026-08-03added
2026-08-03Routinenew design-stage project appeared