Electrical upgrades and generator addition at The Bridge

Dallas · Dallas Bonds

This city’s feed has changed within the last week. We check every morning.

StatusUnder Construction
Stageactive
StartSep 2026
CompletionApr 2027
Budget$2,189,556
CityDallas
SourceDallas Bonds
Source IDdallas_bonds:1019925
Amount paid$381,427
Bond amount$1,800,000
CategoryHomeless Assistance Facilities
Construction award2026-08-25
Current commitment$2,084,234
Design award2025-11-12
Design complete2026-04-15
District(s)Citywide
Original budget$1,800,000
ProgramHomeless Assistance Facilities
Program year2024
Project IDOH24YI08

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-26Notablestart date slipped ~6 weeks
2026-10-14Majorconstruction started