Cobb St from Cobb St to Adair St
Dallas · Dallas Bonds
This city’s feed has changed within the last week. We check every morning.
| Status | Under Design |
|---|---|
| Stage | design |
| Start | Apr 2027 |
| Completion | Jan 2029 |
| Budget | $95,802 |
| City | Dallas |
| Source | Dallas Bonds |
| Source ID | dallas_bonds:1011951 |
| Amount paid | $4,128 |
| Bond amount | $110,305 |
| Category | Street Reconstruction Local Streets |
| Construction award | 2027-01-20 |
| Current commitment | $90,387 |
| Design award | 2019-04-10 |
| Design complete | 2026-09-27 |
| District(s) | 14 |
| Original budget | $110,306 |
| Program | Street and Transportation |
| Program year | 2017 |
| Project ID | PB17V288 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-08-26 | Routine | budget cut 1% ($96,965 -> $95,802) |