StatusUnder Design
Stagedesign
Budget$86,592
CityDallas
SourceDallas Bonds
Source IDdallas_bonds:1020860
Amount paid$31,008
Bond amount$86,592
CategoryVision Zero/Safety
Current commitment$86,592
District(s)14
Original budget$86,592
ProgramStreet and Transportation
Program year2024
Project IDTP24Y471

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed