West Riverside Reclaimed Water Main
Austin · Austin Project Explorer
This city’s feed has changed within the last week. We check every morning.
| Status | Construction |
|---|---|
| Stage | active |
| Start | Jun 2026 |
| Completion | Dec 2027 |
| Budget | $6,396,904 |
| City | Austin |
| Source | Austin Project Explorer |
| Source ID | austin_project_explorer:5267.097 |
| Category | Water |
| District(s) | 9 |
| Finish (raw) | Anticipated Winter 2027-28 |
| Spent to date ($) | $5,691,248 |
| Start (raw) | Summer 2026 |
| Sub-category | Reclaimed |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
| Seen | Rank | Change |
|---|---|---|
| 2026-10-27 | Critical | 31 projects: construction started |