Waller Creek District - Confluence Link - The Confluence Project

Austin · Austin Project Explorer

This city’s feed has changed within the last week. We check every morning.

StatusConstruction
Stageactive
StartMar 2023
CompletionSep 2026
Budget$95,658,644
CityAustin
SourceAustin Project Explorer
Source IDaustin_project_explorer:12861.002
CategoryWater
District(s)9
Finish (raw)Anticipated Fall 2026
Spent to date ($)$88,618,642
Start (raw)Spring 2023
Sub-categoryStormwater

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-27Routinecompletion date notched one reporting quarter (2026-06-01 -> 2026-09-01)