Joan Means Khabele Bathhouse Rehabilitation at Barton Springs Pool

Austin · Austin Project Explorer

This city’s feed has changed within the last week. We check every morning.

StatusConstruction
Stageactive
StartDec 2023
CompletionSep 2026
Budget$21,977,934
CityAustin
SourceAustin Project Explorer
Source IDaustin_project_explorer:6066.035
CategoryFacilities
District(s)8
Finish (raw)Anticipated Fall 2026
Spent to date ($)$21,414,922
Start (raw)Winter 2023-24

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-27Routinecompletion date notched one reporting quarter (2026-06-01 -> 2026-09-01)