StatusActive
Stagedesign
StartSep 2027
CompletionSep 2028
Budget$8,423,795
CityAustin
SourceAustin Project Explorer
Source IDaustin_project_explorer:2231.411
CategoryWater
District(s)8
Finish (raw)Anticipated Fall 2028
Spent to date ($)$1,627,955
Start (raw)Anticipated Fall 2027
Sub-categoryWastewater

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-27Routinestart date notched one reporting quarter (2027-06-01 -> 2027-09-01)