Center Street Pump Station Replacement and Electrical Improvements

Austin · Austin Project Explorer

This city’s feed has changed within the last week. We check every morning.

StatusActive
Stagedesign
StartDec 2028
CompletionSep 2031
Budget$67,824,618
CityAustin
SourceAustin Project Explorer
Source IDaustin_project_explorer:2006.059
CategoryWater
District(s)3
Finish (raw)Anticipated Fall 2031
Spent to date ($)$11,732,408
Start (raw)Anticipated Winter 2028-29
Sub-categoryWater

This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.

What has changed

SeenRankChange
2026-10-27Routinestart date slipped ~6 months