2020 Bond Local Safety/Vision Zero Speed Management (21B)
Austin · Austin Project Explorer
This city’s feed has changed within the last week. We check every morning.
| Status | Construction |
|---|---|
| Stage | active |
| Start | Mar 2024 |
| Completion | Sep 2026 |
| Budget | $2,424,837 |
| City | Austin |
| Source | Austin Project Explorer |
| Source ID | austin_project_explorer:13241.001 |
| Category | Mobility Infrastructure |
| District(s) | 3 |
| Finish (raw) | Anticipated Fall 2026 |
| Spent to date ($) | $2,170,147 |
| Start (raw) | Spring 2024 |
This source does not publish a per-project page, so there is nothing to link to. The fields above are everything the city publishes.
What has changed
Nothing since we started tracking this project. We check every morning.